Cork County Council guide to lodging a BC(A)R commencement notice
The following informative 8 page guide was issued by Cork County Council on 3rd June 2014 to help professionals with lodgment of commencement notices under the new Building Control Management System (the new building regulations). Applicants will be grateful to Cork County Council for providing this most helpful guide for those trying to navigate the complexities of the new BC(A)R system.
Some of the user issues highlighted are the accuracy of information uploaded (no provision to delete once uploaded) and inclusion of valid professional details (see previous posts on this). In the guide they note that there is no retrospective mechanism for compliance under the new building regulations for projects completed without valid commencement notices. They also highlight some of the system issues that affect the BCMS and document lodgment procedure currently.
In the advice (page 1) they note that currently 7 day notices cannot be finalised online using the BCMS as a statutory declaration must be submitted as a hard copy.
In addition Cork County Council have stated that they require the ‘Designer’ to be a registered professional. This may need to clarified as we would assume they mean Design Certifier rather than Designer (see page 3). The requirement in the new regulations is for design certifier (and assigned certifier) to be a registered chartered surveyor, engineer or architect only. There are also issues associated with groups of buildings coming under one commencement notice that may affect validation on completion (page 6)- an important section for phases of residential units under construction.
This is a very useful document and we suggest it may be applicable to other Local Authorities also.
PDF of Cork County Council alert:
cork co co warning 3rd june 2014
.jpeg of alert document:
Other posts of interest:
Building Control Officers Survey – click link here
BReg Blog ALERT: Data Protection & BCMS – click link here
Is anyone checking if certifiers are registered? click link here
No checks of Designer, Builder or Assigned Certifier on BCMS – click link here
BCMS- are we getting what is said on the label? – click link here
The BCMS system: a quickstart guide- click link here
Minister Hogan rejects Irish Times Article – click link here
Pingback: Top 10 for June 7th | BRegs Blog
Pingback: Top 10 for June 7th | BRegs Blog
Pingback: Minister-”Compliance matters that may go unnoticed…” | BRegs Blog
Pingback: Minister-”Compliance matters that may go unnoticed…” | BRegs Blog
Pingback: Opinion: Are builders + developers off the hook with BCAR? | BRegs Blog
Pingback: Opinion: Are builders + developers off the hook with BCAR? | BRegs Blog
Pingback: Where is the Design Certifier in BC(A)R SI.9? | BRegs Blog
Pingback: Where is the Design Certifier in BC(A)R SI.9? | BRegs Blog
Pingback: Top 20 for July 2014. | BRegs Blog
Pingback: Top 20 for July 2014. | BRegs Blog