BC(A)R SI.9 System of Inspections doesn’t work | Michael O’Neill MRIAI

09 February 2017

The following response to an earlier post “How many inspections does a build need ? Mark Stephens MRIAI” by Mark Stephens on 27th December 2016

I am reading a lot of sense in what both Mark and Michael have stated above.  I am well used to both their utterances from reading Mark’s own Blog and Michael’s comments here.  The fact that they are talking sense does not therefore surprise me.

However.. The process of inspection – whether by an overworked architect/ engineer/ building surveyor OR by a team of government-sponsored inspectors – is doomed to fail under the terms of reference of the current legislation and the certificates required under it.  This is not to denigrate what has been written above but to underline the fact that the government have set the certification standards impossibly high while failing to provide the legal tools to certify even to the level that was possible under the previous RIAI Opinions of Compliance

Reasonableness was abandoned the day “compliance” (for which read Absolute Compliance) was substituted for “Substantial Compliance” (for which read Compliance Within Reason And What It Is Humanly  Possible To Inspect).  The current BC(A)R Legislation requires two corporeal persons (not companies) to Certify the Design and Built Work. One corporeal person could do both jobs in theory, but lets consider two of them.

The Design Certifier is required to Certify ALL ELEMENTS OF THE BUILDING ARE DESIGNED COMPLIANTLY – not just those elements that the Design Team Designs

The Assigned Certifier is required to Certify ALL ELEMENTS OF THE BUILT WORK ARE BUILT COMPLIANTLY – not just those elements that the Main Contractor assembles on site from raw materials.

Design, under BC(A)R includes all the locks, light fittings, fire detection and alarm equipment, door lock and door hinge internals, MVHR motor internals, MVHR ducting materials design, Insulation design – to name but a few items not designed by the Design Team and more importantly, which are not possible to be assessed by them through visual inspections.

The Built Work, under BC(A)R includes all elements manufactured off site – timber and steel roof trusses, window and door systems, glazing and roofing systems, bricks, insulation, services piping and wiring, pumps, generators, motors, batteries, door leaves, ironmongery and locks, fire detection and alarm systems, lighting and signage – to name but a few items the Main Contractor is unlikely to witness being created, never mind the Assigned Certifier.

When I refer to standards of certification being impossibly high I mean that it is not physically possible for even the Main Contractor to visually inspect everything that is constructed on site, never mind the sole Assigned Certifier.  Similarly it is not possible for the Design Team to monitor and supervise the design of every element that makes up a building, never mind the sole Design Certifier

Under the previous RIAI Opinion system, it was possible to rely to some degree on Schedule A Assurances, which were defined in the Opinion Wording in terms of source, scope and level of responsibility.  These might include Certificates regarding Design from other Design Team members as well as specialist suppliers, the main contractor, sub-contractors as well as  Certificates regarding elements of the Built Work, which might include Guarantees, Warranties, FAT tests, etc.  No counterpart of these Schedule A Assurances exists in the BC(A)R Legislation.

What about Ancillary Certificates?

This term is mentioned in the reference to certification, but the term is not legally defined.  More importantly, the acceptable sources, scope and level of responsibility are not defined.  Legally therefore, Ancillary Certificates do not exist and any assurance they could possibly offer cannot be relied upon by either the Design Certifier or Assigned Certifier.

Don’t Structural Engineers know what they are doing?

Structural Engineers sample statistically.  They take test samples of mixes for concrete for example.  They do slump tests.  They cast cylinders and send them off for testing.  Statistical sampling lets you state a building is Substantially Compliant.  Statistical sampling in my opinion does not have enough credibility to allow a Certifier to claim a building is Absolutely Compliant.

And that I submit is where this matter rests in terms of Inspections and Certification.  None of the comments above (neither mine nor the two previous writers) address the real issue; –

“A speedy remedy for the Purchaser of a defective property”

That is another day’s work.

The above post was written and submitted by Michael O’Neill MRIAI

Other posts of interest:

How many inspections does a build need ? Mark Stephens MRIAI

Is the Design Certifier a ‘Patsy’ for Builders?

Is Design Certification credible? Michael O’Neill MRIAI

Garland Consulting Engineers | Are third party Design Certifiers compliant?

Ten Point Plan for Building Control Regulations | Mark Stephens MRIAI

Which Dublin GE16 Candidates Favour Independent Building Inspections? Dublin Inquirer

Collins & O Cofaigh- A BETTER way: BC(A)R SI.9 Solutions

Building Control Inspections should be independent | RIAI

How much would 100% independent inspections by Local Authorities cost?

SI.9 – Problems with BCMS Inspection Plans | Barry Kelly MRIAI

Pyrite: the spiraling cost of no Local Authority Inspections

Practical Post 9: Fees & numbers of inspections? BC(A)R SI.9

UK + Ireland | take a quick trip to Holyhead with Breg Blog…

Completion Certificates for Multi-unit Housing

BCMS Completion Stage | No Ancillary Certificates required!

‘Onerous’ Building Regulations must be amended – Minister Kelly

SI.9 completion stage and the BCMS | Clouds are gathering!

Ancillary Certificates: Why On Earth Would You Want To Sign That?

One thought on “BC(A)R SI.9 System of Inspections doesn’t work | Michael O’Neill MRIAI

  1. Nial Murphy Chartered Engineer

    A simple, succinct and entirely accurate summary of the position which has been obvious to me from day 1, and is why I have refused to act as an AC

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *