Building Control threat to Homeless ‘Hubs’ completions?

13 June 2017

At a Dublin City Council (DCC) meeting yesterday, Councillor John Lyons (People Before Profit Alliance) posted on social media that DCC had not consulted councillors regarding homeless ‘hub’ accommodation and that elected representatives had not seen any cost-benefit analysis for any of the emergency schemes.  His motion to ‘cease immediately with this flawed and shameful plan of placing families into industrial estate locations such as the former Bargaintown furniture store… and seek instead solutions to the homelessness crisis, such as acquisitions and a programme of social housing…” was ruled out of order.

In 2015 Architect Vivian Cummins examined the implications of Building Control Regulations introduced in 2014 BCAR SI9 on 22 ‘Rapid’ build homes in Poppintree, Ballymun. His analysis was prescient as the completion of the ‘rapid’ units took 6 months and not 6 weeks as officials predicted, with families moved in May 2016. Vivian Cummins said “Anyone at the frontline of Ireland’s homelessness crisis knows that there is only one crucial factor to be considered in the provision of modular homes and that is speed of delivery. The parents trying to provide meals from a wardrobe in a hotel room, to the 1,500 children currently homeless in Ireland, are not concerned about Building Energy Ratings or timber versus carpet floor coverings. They just want their own roof over their heads in time for Christmas or indeed anytime soon.”

The same ‘red tape’ may affect the Minister’s planned change of use of various different buildings into emergency Homeless ‘Hubs’, temporary emergency accommodation for homeless families. BCAR SI9 procedures affect all change of use applications irrespective of whether any significant internal modifications are needed or not, and there is no exemptions for emergency or temporary buildings under SI9.

Dublin City Council and the Department of the Housing have quite a challenge to deliver accommodation to +7,500 men, women and children by the 1st July.

It is assumed that these projects will be fast-tracked through the planning process by using Section 179 (6) (b) of the Planning & Development Act 2000*- bypassing the normal planning process as the Local Authority deems the situation to be an emergency. The council can skip taking any submissions or observations from the public on the proposal, a process that would normally take a minimum of six weeks.

Building Regulations (the design and construction of the houses) and Building Control Regulations (supervision and enforcement of the Building Regulations) are not as straightforward. The Building Regulations and the Building Control Regulations do not distinguish a “temporary” and a “permanent” dwelling and there are no derogations for an emergency situation, as we have observed with delays in Poppintree. All change of use projects are subject to the same procedures.

Legislation introduced only on 1st September 2015 (SI.365, brought Local Authorities into the BC(A)R SI.9 net they now have to comply with SI9 in full. The problems associated with SI.9 in trying to deliver housing quickly and economically have been seen elsewhere.

The Building Control Regulations require the serving of a Commencement Notice 14-28 days to the Building Control management System (BCMS) before starting on site and a Completion Certificate, at the earliest, 3-5 weeks before completion. It is unclear who will be the ‘Assigned Certifier’ and ‘Building Owner’ for the purposes of submitting the required Commencement Notice and Completion Certificate and undertaking the responsibility for same.

The above means some of the following programme issues for a completion by July based on tenders submitted say by the end of last month (wed 31st May). Allow a one week assessment of tenders with the successful bidder notified on 7th June:

  • There is a 14 days standstill period before the contract can be awarded, so this takes us to 21st June for the earliest possible start on site.
  • To start on site on 21st June a Commencement Notice with full BCAR SI.9 documentation must be lodged online to the BCMS, 14- 28 days before starting on site, so say 7th June at the latest. This is the day that the contractor may be notified that he has been selected.
  • This means that the Design Certifiers, Assigned Certifier and Builder must be appointed and have full documentation lodged last week (before the contract is awarded).
  • Starting on site on 21st June, the builder then has to work back from 1st July contract completion date.
  • This means the builder/developer has to lodge Completion  documents, confirming the building is correctly built, 3-5 weeks before 1st July, before he starts on site.
  • Many issues remain around the submission of Completion Certificates for multi-unit housing that have yet to be resolved.
  • These multi-family projects cannot be occupied until the Local Authority confirms that the houses are on the Register. If there is any delay here the prospective Completion documents will have to be lodged before projects have started.

Have the implications of the Building Control Regulations BC(A)R SI.9 created a scenario where the Assigned Certifier will have to confirm all of his inspections and everyone else’s before the building actually starts in order to meet the completion deadline?

*To be confirmed

Helpful Links: What are the Building Control rules for converting buildings?

The beginners guide:  Practical posts 3: Change of Use – FDI and offices

The expert guide: O’Cofaigh: fit-outs that are exempt from SI.9

 

Other posts of interest: 

Is Building Control a threat to Christmas completion of modular homes? | Vivian Cummins

BCMS Alert | Last day for Christmas Completion! 

Completion Certificates for Multi-unit Housing 

Housing crisis rumbles on… the shape of things to come? 

DECLG Information Note |  SI.365 of 2015 

Getting Our Housing in Order | Vivian Cummins

Share this:

Leave a Reply

Your email address will not be published. Required fields are marked *